Riverhead Volunteer Ambulance Corps: where the funding comes from

A line-by-line look at the Town’s Ambulance District budget, the contract with RVAC, and the 2026 adjustments that corrected the original appropriation.

Independent, unofficial projectData last refreshed November 23, 2026Recently refreshedSee data update details →

In plain English

The key distinction: RVAC’s contract is one line inside a much larger Ambulance District budget. The original adopted 2026 budget set that line at $1,274,924. Resolution 2026-156 moved $100,000 out of the RVAC line to other Ambulance District lines; Resolution 2026-470 later added $99,322 back. The calculated line after both changes is $1,274,246—$678 below the original adopted amount. The May addition used $80,000 of fund balance and a $19,322 reduction to the vehicle line. These are budget authorizations, not a claim that this exact amount has already been paid.
  • RVAC: Riverhead Volunteer Ambulance Corps, the service provider paid under contract.
  • Ambulance District: A separate Town fund (SM1), not the Town General Fund. Its revenues and reserves are not interchangeable with General Fund money.
  • Budget vs. cash: An appropriation is permission to spend, and a revenue estimate is a plan. Neither proves how much was ultimately collected or paid.
  • Fund balance: Accumulated surplus from earlier years. Using it can fund a one-time shortfall, but it is not recurring revenue.
2026 adopted fund budget
$2,388,824
Before the in-year adjustments
Known revised fund budget
$2,513,824
Adds $80,000 for RVAC and $45,000 for Armory repairs from fund balance
RVAC contract line
$1,274,246
After Resolutions 2026-156 and 2026-470
Fund-balance draw for correction
$80,000
Explicitly listed in Resolution 2026-470

1. How the 2026 Ambulance District was funded

The adopted budget balanced $2,388,824 in planned revenues with $2,388,824 in planned expenditures. Property taxes are the largest revenue source; ambulance billing is the second-largest. The billing figure is an estimate in the budget, not audited collection data.

Revenue sourceAccount2025 actual2026 adoptedYTD to Jun. 30Budget shareWhat it means
Property taxesSM1-1001-001-00000-A$1,658,800$1,704,224$1,704,22471.3%The district’s main tax-supported revenue.
LIPA PILOTSM1-1081-100-00000-B$43,296$43,300$01.8%Payment in lieu of taxes.
Ambulance charges — medical billingSM1-1640-000-00000-4$205,790$640,000-$205,79026.8%2025 actual and 2026 YTD are equal and opposite; the journal entry needs explanation.
Ambulance charges — full billingSM1-1640-100-00000-4$0$0$00.0%Separate revenue line; budgeted at $0 in 2026.
Interest and earningsSM1-2401-000-00000-G$37,419$1,300$15,1210.1%Budget estimate.
Total revenue$1,945,305$2,388,824$1,513,554100.0%2025 actual, 2026 adopted, and YTD through June 30.

The Town’s 2027 Budget Supplement reports $1,513,554 in total Ambulance District revenue through June 30, 2026. Its medical-billing line is negative $205,790, exactly offsetting the $205,790 reported as 2025 actual medical-billing revenue. That exact reversal may reflect a reclassification or journal entry, but the supplement does not explain it. The ledger and billing-reconciliation detail are needed before drawing conclusions about collections. The 2025 budget had $2,710,749 estimated on the separate “Full Billing” line and $100,000 on medical billing, but the supplement reports $0 actual full-billing revenue for 2025 and $205,790 actual medical-billing revenue. The 2026 adopted budget zeroed the full-billing line and estimated $640,000 in medical billing. The identical negative 2026 YTD medical-billing amount should be reconciled to the underlying journal entries.

As of June 30, 2026: what the supplement reports

The Town’s 2027 Budget Supplement lists year-to-date expenditure figures through June 30, 2026. They are an interim accounting snapshot, not the final 2026 result.

Expenditure categoryYTD to Jun. 30Interpretation
RVAC professional-services line$350,298Reported 2026 YTD amount; not the final annual payment total.
Ambulance function subtotal$429,585Includes RVAC plus vehicles, repairs, fuel, utilities and administration.
Insurance$66,527Liability insurance and claim payments.
Transfer to General Fund debt service$0No YTD amount shown in the supplement.
RVAC & Improvements Reserve contribution$0No YTD contribution shown in the supplement as of June 30.

The supplement’s RVAC line shows $1,174,924 in its “2026 Adopted Budget” column, while the original adopted-budget page shows $1,274,924. The difference matches the February $100,000 reallocation described below. The May resolution then adds $99,322 back. We show both documents rather than silently treating their differently timed figures as the same thing.

2. Where the adopted budget planned to spend the money

The contract is not the entire budget. Alongside ambulance operations, the district budgeted a transfer to General Fund debt service, a reserve contribution, and insurance. Those items serve different purposes and should not be described as payments to RVAC.

Budget lineAccount2026 adoptedExplanation
RVAC service contractSM1-4-4540-436-203-00000$1,274,924Adopted starting amount, before the two adjustments below.
Vehicles / equipmentSM1-4-4540-280-000-00000$85,000Vehicle and equipment appropriation.
Building maintenanceSM1-4-4540-402-000-00000$25,000Repairs and maintenance — buildings.
Vehicle repairsSM1-4-4540-405-000-00000$45,000Repairs and maintenance — vehicles.
FuelSM1-4-4540-426-000-00000$35,000Gasoline and diesel.
Office rentSM1-4-4540-462-100-00000$6,900Rents and leases — office.
TelephoneSM1-4-4540-471-000-00000$6,000Utilities.
ElectricitySM1-4-4540-472-000-00000$25,000Utilities.
Heating fuel / oilSM1-4-4540-473-000-00000$10,000Utilities.
WaterSM1-4-4540-474-000-00000$2,000Utilities.
Administrative chargesSM1-4-4540-495-000-00000$164,400Administrative charges allocated to the district.
Ambulance operations subtotal$1,679,224Includes the original RVAC contract line.
Transfer to General Fund debt serviceSM1-9-9901-900-V01-00000$450,000An interfund transfer, not an RVAC contract payment.
RVAC & Improvements Reserve contributionSM1-9-9990-000-000-00000$190,000Money budgeted to be set aside, not an operating expense paid to RVAC. The 2025 adopted reserve contribution was $2,536,549; the 2026 contribution was reduced to $190,000. These annual appropriations are not the reserve’s cash balance.
InsuranceSM1-1-1910$69,600General liability insurance premiums and claim payments.
Total adopted expenditures$2,388,824Matches planned revenue.

3. The two 2026 corrections to RVAC’s contract line

FEBRUARY 18, 2026 · RESOLUTION 2026-156

Move $100,000 out of RVAC to other ambulance lines

The resolution corrected several lines that the original adopted budget had left at different amounts. The Town’s 2027 Budget Supplement’s 2026 column shows vehicles at $105,000, other professional services at $30,000, equipment rent at $50,000, and RVAC at $1,174,924—a pattern consistent with moving $100,000 out of RVAC and into those three lines. The original 2026 adopted budget instead shows vehicles at $85,000, the other two lines at $0, and RVAC at $1,274,924. The supplement appears to incorporate this February adjustment even though it labels the column “2026 Adopted Budget”; that difference is important to disclose.

Other district line increasedAmount moved from RVAC
Vehicles / equipment$20,000
Other professional services$30,000
Equipment rent / lease$50,000
Total moved out of RVAC$100,000

Adopted unanimously. The minutes record Supervisor Halpin and all four council members voting yes.

MAY 20, 2026 · RESOLUTION 2026-470

Add $99,322 to RVAC’s line, including $80,000 from fund balance

This resolution added $99,322 to the contract line. It reduced the vehicle line by $19,322 and charged $80,000 to the district’s “Appropriated Fund Balance” account. Because the vehicle reduction offsets part of the addition, the net increase to the fund budget is $80,000—not $99,322.

Funding / offsetAmountEffect
Reduce vehicles / equipment$19,322Reallocated from another district line.
Appropriated Ambulance District fund balance$80,000One-time accumulated savings, no new recurring revenue.
Total added to RVAC contract$99,322Net district budget increase: $80,000.

Adopted unanimously by the four members present; Councilman Robert Kern was absent. Supervisor Halpin voted yes.

What changed after both resolutions?

Original 2026 RVAC contract appropriation$1,274,924
February reallocation out of RVAC−$100,000
May contract adjustment+$99,322
Revised RVAC contract appropriation$1,274,246

Compared with the 2025 adopted RVAC line of $1,347,300, the calculated revised 2026 appropriation is $73,054 lower (5.4%). That comparison is between budget authorizations, not audited cash payments.

4. Contract history: the adopted RVAC line

Budget yearAdopted RVAC lineReading
2020$1,165,000Adopted budget line; not actual cash paid.
2021$1,231,700Adopted budget line; not actual cash paid.
2022$1,244,100Adopted budget line; not actual cash paid.
2023$1,280,279Adopted budget line; not actual cash paid.
2024$1,308,189Adopted budget line; not actual cash paid.
2025$1,347,300Adopted budget line; not actual cash paid.
2026$1,274,924Before the two adjustments above.
2026 after adjustments$1,274,246Calculated from Resolutions 2026-156 and 2026-470.

5. What the 2027 budget sets

The Town Board adopted the 2027 budget on November 17, 2026. Its October 20 amendments did not touch the Ambulance District, so the adopted budget carries the same figures as the Supervisor’s Tentative. It sets a larger RVAC contract line, while reducing the planned debt-service transfer and reserve contribution and lowering the medical-billing revenue estimate.

2027 adopted Ambulance District budget
$2,312,093
Down from the 2026 adopted plan of $2,388,824.
2027 adopted RVAC line
$1,401,731
$127,485 above the calculated post-resolution 2026 line.
Property-tax revenue
$1,751,693
$47,469 above the 2026 adopted estimate.
Medical-billing estimate
$514,000
$126,000 below the 2026 adopted estimate; not actual collections.
2027 adopted lineAmountCompared with 2026 adopted plan
Ambulance function, including RVAC$1,826,231Includes a proposed RVAC line of $1,401,731.
Insurance$36,732Down from $69,600.
Transfer to General Fund debt service$324,000Down from $450,000.
RVAC & Improvements Reserve contribution$125,130Down from $190,000; this is the budgeted contribution, not the reserve balance.
Total proposed expenditures$2,312,093Balanced to the proposed revenue plan.

The Town’s 2027 Budget Supplement uses $1,174,924 as the 2026 comparison value for RVAC, apparently reflecting the February reallocation but not the May addition. The proposed 2027 line is therefore best compared with both the published supplement and the calculated post-resolution 2026 line; neither is a substitute for the final 2026 ledger. Review the 2027 Tentative Budget analysis →

6. New headquarters: donations, a Town bond, and lease payments

The new ambulance headquarters is a separate capital project—not part of RVAC’s annual service-contract line above. The September 1, 2026 public-hearing notice put the project’s estimated maximum cost at $14.1 million. The stated financing plan was $6 million provided by RVAC from private fundraising and other available funds, with the balance—up to $8.1 million—financed through Town-issued bonds. At the hearing, the Supervisor said fundraising was then just under $6.5 million. Those are reported project-financing figures, not proof of the final construction cost, final donations received, or bonds ultimately issued.

Maximum project estimate
$14.1 million
Estimated maximum cost in the public-hearing notice.
RVAC private funding
$6.0 million
Formal financing plan; later public remarks said fundraising was nearly $6.5 million.
Town bond authorization ceiling
$8.1 million
Maximum planned bond financing, not confirmation of the amount actually borrowed.
  • Ownership: the new building is to be owned by the Ambulance District and leased to RVAC.
  • Repayment plan: the public notice and hearing record say the lease agreement requires payments from RVAC to the district sufficient to cover bond debt service. The stated plan relies on ambulance-billing revenue generated by services RVAC provides.
  • Risk distinction: “planned to be paid by RVAC” is not the same as proof that the Town has no financial exposure. The bond documents, executed lease, actual billing collections, debt-service schedule and any guarantee or backstop determine who bears the risk if collections fall short.
  • Timeline: while the existing headquarters is replaced, RVAC temporarily operates from the Town-owned Armory. Resolution 2026-842 appropriated $45,000 from Ambulance District fund balance for Armory building repairs. That is a separate operating-fund adjustment, not part of the $8.1 million bond ceiling.
  • Other Town facilities: 2026 resolutions also authorized temporary use of Town space for EMT instruction, medical billing / records storage and ambulance vehicle storage. The resolutions identify the uses, but do not provide a dollar value for that space or establish whether rent was charged.

How ambulance billing is supposed to repay the building bond

  1. RVAC responds and transports patients. Depending on the service and coverage, a bill may be submitted to Medicare, Medicaid, a private insurer, or the patient.
  2. Billing produces collections. The gross amount billed is not the same as cash collected: insurer allowed amounts, denials, write-offs, patient responsibility and timing all affect receipts.
  3. The lease is the repayment bridge. The Town’s bond hearing notice says the lease must require payments from RVAC to the Ambulance District sufficient to cover the bond’s debt service. Public statements describe ambulance-billing receipts as the expected source for those payments.
  4. The District pays the bond debt service. Principal and interest are paid according to the bond schedule. The key test is whether the lease payments actually received, supported by available billing cash, cover each scheduled payment when due.

Important accounting distinction: ambulance billing is the expected economic source of repayment; it is not proof that each dollar collected is automatically deposited into a legally restricted bond account. The public hearing notice establishes the lease-payment requirement, but the detailed executed lease, revenue pledge or assignment, debt-service schedule, collection reports and annual reconciliations are needed to verify the exact cash path.

What should be published each year

  • Gross ambulance charges, collections received, contractual adjustments, write-offs and accounts receivable.
  • Net billing cash available after the cost of billing and other required operating expenses.
  • Lease payments due and received from RVAC, with dates and amounts.
  • Bond principal, interest and fees paid; remaining principal; and any reserve or fund-balance support used.
  • Any shortfall between lease receipts and debt service, including which entity is legally responsible and what funding source covers it.

Sources: Town’s September 1 public-hearing notice (reproduced by RiverheadLOCAL); September 1 Town Board hearing and bond resolution; RiverheadLOCAL’s project and lease reporting; RVAC’s headquarters fundraising page; Town Board Resolution 2026-842 (September 15).

7. What this record does—and does not—prove

  • The original adopted RVAC line was $1,274,924. After the February reduction and May addition, the calculated line is $1,274,246, just $678 below the original amount.
  • Resolution 2026-156 moved $100,000 out of RVAC into other district lines; Resolution 2026-470 added $99,322 back, including $80,000 from fund balance. Resolution 2026-842 later added $45,000 from fund balance for temporary Armory repairs.
  • The Ambulance District is separate from the General Fund. These resolutions do not show a $450,000 General Fund shortfall; they document a specific correction to the district’s RVAC contract line.
  • The 2026 budget also contains $450,000 for a transfer to General Fund debt service and $190,000 for the RVAC & Improvements Reserve. Neither line is itself the RVAC service-contract payment.
  • The available budget and resolutions do not establish the final amount paid to RVAC, explain the negative YTD medical-billing figure, establish the current reserve balance after all transactions, or show whether further adjustments occurred after the records reviewed. Those require year-end ledger / audited actuals and the full contract-payment ledger.

Sources and related views

Method: amounts marked “adopted” are from the Town’s 2026 budget. Revised figures are arithmetic from the cited resolutions. The page distinguishes planned revenues, spending authority, transfers, and reserve contributions; it does not treat them as interchangeable cash flows.

Independent public-records guide for Riverhead residents.

Riverhead Budget Live is an independent project. It is not run, approved, or endorsed by the Town of Riverhead. The site organizes public information and provides analysis; it is not a substitute for the Town’s official records. Check the linked source documents before relying on an important figure. Basic, aggregated site-usage statistics are collected through Google Analytics. You do not need an account to use this site. There are no ads. If you’d like to help cover its costs, you can chip in on Ko-fi.

Color an increase: