The Town's largest downtown project, gathered in one place — what is being built, how the land was assembled, and what the $1,950,000 taking of 111 East Main Street and the note paydown do to the General Fund balance.

Independent, unofficial projectData last refreshed November 23, 2026Recently refreshedSee data update details →

In plain English

On September 1, 2026 the Town Board voted unanimously to offer $1,950,000 for 111 East Main Street — the building intended for the Long Island Science Center — and to pay for it out of the General Fund balance. That follows a court vesting order on August 26 and an August 4 vote paying down the project's note from fund balance until the hotel-site sale closes. Two draws on accumulated surplus for one project, which is why they are shown together below.
  • Eminent domain: a government taking private property for public use, which it may do — but it must pay fair value, and the owner can argue in court about what fair is.
  • Vesting order: the court order that transfers title. Once it and the acquisition map are filed with the county clerk, the land is the Town’s.
  • Fund balance: accumulated surplus from past years. Spending it is not borrowing — no interest, no repayment — but it is finite, and it is the cushion the reserve policy exists to protect.
Calculated from source data. Computed by the site from cited source records; it is not a separate Town-reported figure.Source: Town Board resolutions 2026-641, 2026-746 and 2026-762; Town Square QE DocumentsAs of: September 1, 2026Calculation: Separates Town land acquisition and fund-balance note paydown from developer construction costs and public grants.Review the source library →

The short version, in six numbers

These are not one budget and should never be added together. They are the separate pots this project moves through, which is the thing most easily got wrong about it.

$34,920,869
Grants awarded
Federal, state and county — the largest pot by far
$32,672,890
Private development
The hotel, financed by the developer
$7,020,000
Land the Town bought
Six parcels and interests since 2020
$1,815,000
Net back from the sale
After documented credits, before construction-management credits
$1,500,000
Town pays the developer
$150,000 a year for ten years to run the square
20 years
Tax abatement requested
Undecided. No hearing scheduled
Part 1

What is being built

The thing itself, and how it changed on paper between 2022 and 2026.

The project as it stands

A public plaza, playground and amphitheatre, together with a five-storey, 92-room hotel and a restaurant, and major site work to carry out flood mitigation along the Peconic Riverfront. A parking garage north of East Main Street is planned separately as part of the same downtown effort.

Where it stands
Construction has started. The Town described itself in August 2026 as moving from planning into construction across six connected downtown projects, with the hotel mobilising first and the parking garage not finished until 2030. Officials have said the overall project cannot be built out while the science center parcel stays unresolved, which is the stated reason for the condemnation described below.

The hotel has been four different buildings on paper

The condominiums were dropped, and that has a tax consequence: The July 2025 budget describes 76 hotel rooms and 12 condominium units — 88 keys, the figure its cost-per-key is calculated on. The approved building has none: 94 rooms, of which 80 are guest rooms and 14 are suites, hotel-only. Twelve owner-occupied condominiums would have entered the assessment roll as taxable residential property paying town, county and school taxes; hotel rooms do not. Laura Jens-Smith asked the Board in June 2026 whether it had evaluated that difference in assessed value, property tax and school tax revenue. No analysis answering that question has been published.
Show all six versions of the building, 2022 to 2026
April 19, 2022Four storeys, 84 rooms
Plus a two-storey building west of the square, a boat house on the river, and a four-storey riverfront condominium building — all since dropped from the plan.
RiverheadLOCAL, April 17, 2024
July 22, 202576 hotel rooms and 12 condominium units
88 keys, which is what the developer’s cost-per-key of $371,283 is calculated on.
Town of Riverhead, Town Square QE Documents
August 4, 2026Five storeys, 94 rooms — approved
A 69,738 sq ft building on roughly 0.42 acres at 117–127 East Main Street, with retail, a restaurant, a café and nine staff parking spaces on the lower level. Branded as a Tapestry by Hilton. This is the version that holds site plan and special permit approval, granted unanimously by resolution 2026-746.
RiverheadLOCAL, August 5, 2026; Town Board resolution 2026-746
June 11, 2026Five storeys, 94 rooms — condominiums gone
80 guest rooms and 14 suites, a Tapestry by Hilton, with a roughly 5,100 sq ft, 116-seat restaurant and bar with terrace seating, a coffee shop and retail, and nine staff parking spaces on the lower level. The fifth-floor condominiums of the earlier scheme are not in it.
RiverheadLOCAL and Newsday, June 11–12, 2026
June 12, 2026About $35.1 million, per the amended IDA filing
The developer’s amended application to the Industrial Development Agency puts total project cost near $35.1 million with about 8,800 sq ft of first-floor retail, restaurant and food-hall space — a later and larger figure than the $32.67 million filed with the Town in July 2025.
RiverheadLOCAL, August 5, 2026
September 2, 2026Described as 92 rooms
Later reporting gives a slightly different count than the approved plan. The approved figure is the one to rely on.
RiverheadLOCAL, September 2, 2026
Part 2

What it costs the public

The money runs in both directions and no published figure nets it out. This is the long part; each section below stands on its own.

Three ledgers, not one

About $74.6 million is going into the Town Square between grants, private development and the Town’s own land assembly. Riverhead’s share — every parcel and interest it has bought or taken — is roughly 9% of that, and part of it was borrowed rather than paid from surplus.

Grants
$34,920,869
Federal, state and county awards. Seven of them, itemised below.
Private development
$32,672,890
The vertical build, financed by J. Petrocelli Development Associates.
Town land assembly
$7,020,000
Every parcel the Town bought or took. Part borrowed, part from surplus — itemised below.

These are not a single budget and should not be read as one. Grants and the developer’s financing pay for different things, on different schedules, and the Town’s figure is land assembly rather than construction. What the comparison shows is scale: the Town’s own cash exposure is small relative to the money moving through the project.

Three ledgers are also not all of it, and the missing pieces run in both directions. The Town expects about $1.8 million net from selling the hotel strips back to the developer. Against that it has agreed to pay the developer $150,000 a year for ten years to run the square, plus 7% of the construction cost of the public works — a rate with no cap and no published base. A twenty-year tax abatement is pending that would forgo revenue nobody has sized. And parking, stormwater and access commitments carry no price at all. Each has its own section below. Nobody has published a single figure that nets these against one another, and this page does not invent one.

Where the $34,920,869 of public money came from

Federal RAISE grant, U.S. Department of Transportation$24,123,369
Secured under the Bipartisan Infrastructure Law. Senator Schumer described it as funding to reclaim the Peconic riverfront for public use, install flood mitigation, spur mixed-use development and make downtown safer for pedestrians and cyclists.
NYS Downtown Revitalization Initiative, Department of State$4,200,000
Riverhead’s downtown won a $10 million DRI award in January 2022; this is the share directed to the Town Square itself.
Empire State Development$3,200,000
Includes the $1,400,000 for the riverfront amphitheatre that the Board accepted by resolution 2025-591 — a part of this line, not an addition to it.
Suffolk County Jumpstart$2,400,000
NYS Parks, Recreation and Historic Preservation$500,000
Brownfield Opportunity Area funds, Department of State$400,000
Suffolk County Downtown Revitalization$97,500
federalstatecounty
As itemised by the Town at the groundbreaking, December 12, 2025.
Who pays for the $32,672,890

Of the $32.7 million, roughly 97% is private — a construction loan and developer equity. The only public money in this budget is a $1,000,000 Restore NY grant awarded in 2024. None of it is Town fund balance. A letter of support in the same filing describes it as “this privately funded project.” Two things qualify that without contradicting it: the budget is a July 2025 snapshot the developer later revised upward to about $35.1 million, and it books cash only — it does not show the tax abatement now pending before the Industrial Development Agency, nor the public commitments listed further down that carry no price.

Construction loan
$19,603,734 · 60%
Developer equity
$12,069,156 · 36.94%
Restore NY grant, awarded 2024
$1,000,000 · 3.06%
Developer's budget as filed July 22, 2025. Named master developer through a Qualified and Eligible review by the Town’s Community Development Agency. A CPA letter dated July 17, 2025 from Piccirillo, Lamont & Giammarese LLP verified J. Petrocelli Contracting’s financial capacity to complete the project.
Money out

What the land cost the Town

The price of assembling the site, whatever it was financed with. This is a different question from the fund balance below — the 2021 purchases were paid for with borrowing, the 2026 taking comes out of surplus, and adding a purchase to the note that financed it would count the same money twice.

Seller: Riverhead Enterprises, for the 2020–21 purchases.

Of the three buildings bought in 2020–21, 117 East Main Street — tax lot 12 — is not part of the sale to the developer. It stays in public hands and becomes part of the square. What is being sold on is 121 and 127, plus an adjoining parcel.

117 East Main StreetAuthorized August 2020, title May 2021$1,250,000
Demolished, to become the square.
121 East Main StreetAuthorized August 2020, title May 2021$950,000
Demolished, to become the square.
127 East Main StreetOption August 2020, title May 2021$2,650,000
Kept and standing. Houses the Chamber of Commerce and the Business Improvement District, and formerly the Craft’d bar. Part of the hotel site.
Six-month purchase option on 127August 2020$50,000
Paid to hold the third parcel while appraisals and environmental work were done.
Craft’d leasehold at 127 East Main StreetCourt order August 27, 2025; settled September 3, 2025$170,000
Bought out from SNR Bar 25 Corp so the building could be demolished. The bar closed on September 20, 2025.
111 East Main StreetAuthorized September 2026$1,950,000
Taken by eminent domain from The Place for Learning. The offer is a floor, not a ceiling.
Known total$7,020,000

The Board authorized $5,500,000 of bonding in August 2020 to cover the purchase price, site work and demolition. The $2,800,000 bond anticipation note issued in August 2021 is part of that authorization rather than money on top of it. The 2026 taking, by contrast, is being paid from fund balance.

One figure is missing: The settlement figure is known — $170,000, with the company to vacate by September 30, 2025 and the Town to pay by October 15. The Board had funded a $120,000 offer six weeks earlier and topped it up on September 16. The full settlement agreement was not attached to the resolution released to the press, so the terms beyond those dates and that number are not public.
Residents could have forced a vote: Both 2020 resolutions were subject to permissive referendum. Residents could have forced a town-wide vote on the purchase and the borrowing with 594 signatures — 10% of the 11,882 who voted in the 2018 governor’s election — within 30 days. No petition was filed.

The Town pays the developer to build and then to run the public square

Town Square Operation & Management Agreement$150,000 a year for 10 years — $1,500,000
Section 3.04(b) and the Article III closing terms. Uniquely among the outstanding documents this fee is already fixed: the parties must complete negotiation of all terms at or prior to closing “with the exception of annual fee set at $150,000.00 per year for 10 year term.” Year one is credited against the purchase price if the square is open to the public by closing.
Three construction management agreements7% of total construction costs, uncapped
Exhibits G, H and I cover the Town Square upper deck and public gathering space, the lower deck and playground, and the East End Arts relocation and amphitheatre. Each is written as a professional services agreement: “Town will pay Consultant the total sum of seven (7%) percent of the total construction costs to be billed for completion of the project,” billed per phase where the design and bid awards are phased, net thirty days. There is no cap and no stated construction cost, so the fee cannot be quantified here — but it is charged on the public half of the project, which the grant table puts at $34.9 million.
The duties are not published: What the Town gets for that $1,500,000 is not published. The agreement points to “a list of responsibilities for operation/maintenance attached hereto as Exhibit ‘J’,” which it says will be incorporated into the Operation & Management Agreement. Exhibit J is not in the copy the Town posts. The document runs to 124 pages and ends with the third construction management agreement; Exhibits A through I are all there and J is not. So the fee is fixed and public while the duties bought with it are neither — and the Operation & Management Agreement itself is still to be negotiated at or before closing, which has not happened.

One protection runs the Town’s way. If the developer defaults on the construction management agreements, a fee of $300,000 becomes due to the Town for its use of the staging areas it was licensed to occupy.

These are ordinary arrangements — a municipality hiring the developer already mobilised on the site is usually cheaper than a separate procurement. They are set out because they are Town expenditures on a project the Town’s own communications describe as privately financed, and neither appears in the grant table or the developer’s budget.

Money back in

The Town is selling most of the site back out

Resolution 2025-696, adopted unanimously August 5, 2025 — moved by Rothwell, seconded by Kern. Terms from the Master Developer Agreement, Section 3.04, executed August 19, 2025.

Purchase price$2,625,000
Grant-match funding commitments− $660,000
Section 3.04(a) itemises three commitments the developer made as part of grant applications for the hotel and the square — $360,000, $150,000 and $150,000. To the extent they have been paid to the Town, they are credited against the balance due at closing.
Year one of the Town Square operation and maintenance fee− $150,000
Section 3.04(b): if the Town has substantially completed the square and opened it to the public by closing, the price drops by $150,000 — year one of the ten-year license under which the Town pays the developer to run and maintain it.
Construction management fees, at the Town’s optionnot published
The Town “reserves the right at its option” to credit against the balance due whatever is then owed, or about to be owed, to the developer under the three construction management agreements. No figure can be put on this: it is 7% of construction costs that have not been published.
Net cash, before any construction-management credit$1,815,000

Take the two credits that carry numbers and the Town nets $1,815,000 in cash at closing, plus real property transfer tax costs which the buyer pays on top. Apply any construction management credit and it is less again. The price also already reflects a credit for the portion of Lot 14 the Town keeps, and already includes the cost of the Lot 13 and Lot 15 strips.

Not whole lots. The “Hotel Property” is four strips: a portion of Lot 14 measuring about 60ʹ × 220ʹ, a portion of Lot 13 at 14ʹ × 200ʹ, a portion of Lot 15 at about 10ʹ × 220ʹ, and a portion of Lot 86.1 at 14ʹ × 20ʹ — roughly 18,500 square feet, which matches the 0.42-acre site in the approved plan. Lot 12, which is 117 East Main Street, and the remaining portions of Lots 13, 14, 15 and 86.1 stay with the Town and become the square itself.

Designating J. Petrocelli Riverhead Town Square LLC a “qualified and eligible sponsor” under the State Urban Renewal Law is what allows the sale without competitive bidding. Town Attorney Erik Howard told the Board in May 2025 that as urban renewal properties these parcels do not require a request for proposals. That is a lawful and ordinary route inside an urban renewal area. It is also the reason no other price was ever tested against this one.

Why the bar had to go: Section 3.03 explains the condemnation in one line. Closing cannot proceed until the Town can convey Lot 14 “free of all leases and rights of tenants,” until structures on the Lot 15 strip are relocated, and until the Planning Board approves the lot line alteration that turns the four strips into one lot. The Craft’d leasehold had to go because the Town had promised to deliver the land without it. The buildings come down at the developer’s sole expense.
It has not closed: The agreement requires closing “not later than one year from the date of this Agreement” — August 2025, so August 2026. It has not closed. The developer exercised a contractual right to push past July 31, 2026, and the pre-possession lease below carries a six-month extension to March 14, 2027. Ron Hariri of Aquebogue called the delay “a red flag” about possible financing or investor issues at the August 4 meeting.

The developer is renting the site, and the rent is the Town’s debt service

Pre-Possession and Lease Agreement between the Town, the Community Development Agency and J. Petrocelli Riverhead Town Square LLC, 2025

The agreement lets the developer take possession of the hotel parcels, demolish what stands on them and begin foundation work before title changes hands. The developer takes the property as is, with no Town warranty of any kind including environmental condition, bears every cost and liability of demolition, and carries $5,000,000 of general liability insurance with the Town named.

Section 3.03 sets the rent at “not less than cost of annual payment due for repayment of bond principal and interest related to purchase and demolition of 117, 121, and 127.” The rent is not a market rent. It is the Town’s carrying cost on the land, passed through.
Monthly rent to August 15, 2026$17,500
Due on the 15th. The first payment was due on execution. Twelve months of it is $210,000, against $209,000 of note debt service — $100,000 principal and $109,000 interest for the year to August 15, 2026.
Monthly rent, six-month extension$19,000
If closing slipped past August 14, 2026 the parties could extend by mutual agreement, running to March 14, 2027 at the higher rate. The closing did slip.
Backstop payment if no closing by March 14, 2027$2,493,750
The purchase price less the 5% deposit. The obligation is “absolute and unconditional without offset or counterclaim,” and the developer consents in advance to the Town releasing the money to pay down the debt.

The agreement states the purpose of that backstop in its own words: the money is to be released “to make payment related to indebtedness necessary to avoid long term bonding.” Without it the Town was required to convert the note into a fifteen-year bond on August 15, 2026 — roughly $175,000 of principal a year at an estimated 3.75%, $2,625,000 of principal over the term and more than $500,000 of interest on top. The purchase price and the bond principal are the same number, which is the whole design: the sale is meant to retire the debt on the land.

Where the protection stops: The protection is not total. The developer must post a performance bond or claw-back letter of credit before excavation, but the Town’s own departments set the amount and it is not fixed in the agreement, and the restoration obligation expressly does not cover the demolished buildings. If the project failed between demolition and closing, the Town would get back a cleared lot rather than the buildings it bought.
Money forgone, and money never priced

A tax-abatement application is pending, and nothing has been decided

Application accepted for review, August 3, 2026. No assistance approved.

What was asked for
Sales and use tax exemptions, mortgage recording tax exemptions, and real property tax abatement through a payment-in-lieu-of-taxes agreement. At the June 2026 hearing the developer’s attorney, Eric Russo, put a term on it: a twenty-year PILOT. Against that he set the project’s jobs case — an estimated 210 construction jobs, 26 full-time and 14 part-time hotel staff, and about 50 more across the ground-floor retail. Those are the applicant’s figures, given at a hearing; no independent verification of them has been published.
What was decided
Nothing yet. The IDA resolution accepts the amended application for review and authorizes Chairman James Farley to engage Camoin Associates to prepare an absorption and impact study at the applicant’s expense. A public hearing must be held before the agency decides, and none has been noticed: the agency’s own public hearing notices page carried nothing for this project when this page was written, its most recent posting of any kind dating to February 2024.
The Town already wrote it into the deal: The Master Developer Agreement does not treat the abatement as an open question. Its recitals state that obtaining a PILOT agreement “is a material requirement of this Agreement,” that the PILOT payment, escalation and term must be “acceptable to Master Developer in its sole, but reasonable, discretion,” and that failing to obtain one on those terms “shall have a material adverse impact on the economics of the transactions contemplated in this Agreement.” The Town signed that in August 2025. The agency that must decide is legally separate from the Town Board and is not bound by it, and no PILOT has been granted — but the Board committed the Town to a deal built on the expectation of one, and wrote in that the developer, not the agency, judges whether the terms are acceptable.
Why it belongs on this page: A PILOT does not spend money; it forgoes it. Property tax abated on the hotel is revenue the Town, the county, the fire district and — the largest share by far — the school district do not collect, which means the cost of running them is spread across everybody else’s assessment for the life of the agreement. None of that appears in the grant table or the developer’s budget, and none of it can be quantified until the IDA acts. What is on the record is that the master developer agreement treats IDA approval of financial assistance as integral to the project.

This page takes no position on whether the abatement should be granted. It notes that a fourth pot of public support is in play, that its size is unknown, and that the decision belongs to a body residents do not elect.

Show how the application got here, who decides it, and what to watch for
What happened
J. Petrocelli Riverhead Town Square LLC applied to the Riverhead Industrial Development Agency for financial assistance in November 2025 and amended the application on June 12, 2026 to reflect the hotel-only plan. The IDA accepted the amended application on August 3, 2026 — one day before the Town Board granted site plan and special permit approval.
The application is not public
The application itself is not public. Newsday reported in June 2026 that it had filed a Freedom of Information Law request to obtain it. So the twenty-year figure above rests on what the developer’s attorney said in a public meeting rather than on a document anyone outside the agency has read.
The project cost in that filing
The amended application estimates total project cost at about $35.1 million — a branded 94-room hotel with roughly 8,800 square feet of first-floor specialty retail, restaurant and food-hall space. That is a later and larger figure than the $32.67 million in the July 2025 development budget shown above.
Who decides
The Riverhead Industrial Development Agency is a public benefit corporation created in 1980, separate from the Town Board and not elected. Its members are James Farley as chair, Lee Mendelsen as vice-chair, Lori Ann Pipczynski as secretary and Douglas Williams as treasurer, with Council Member Joann Waski as Town Board liaison. It has the authority to issue industrial development bonds and to grant real property tax abatements, sales and compensating use tax exemptions and mortgage recording tax exemptions — the three things sought here. It meets at 5pm on the first Monday of each month at Town Hall, and the meetings are open.
What to watch for
When the hearing is noticed it will appear on the Riverhead IDA’s public hearing notices page, linked in the sources below. Judging by what the agency posted for comparable applications, the notice is usually accompanied by the application itself, a Camoin Associates report, a cost-benefit calculator and the authorizing resolution — which together are the documents that would let a resident work out what the abatement is worth and who bears it. That hearing is the point at which the public can be heard on this, and it is the only one.

What abatements this agency has granted before

The pattern is legible without any arithmetic on the hotel: commercial and mixed-use projects downtown have generally received about ten years, affordable housing thirty, and the one existing hotel four. The request on the table is for twenty. That is roughly double what this agency has given comparable downtown commercial projects and five times what it gave the other hotel, and it is the single most checkable thing a resident can carry into the hearing. It is not a reason the request should be refused — the agency weighs jobs, investment and blight, not precedent alone — but it is the question the agency will have to answer.

Show the eight agreements this agency has granted, with terms

The Petrocelli hotel is not on this list. Its application has been accepted for review, not approved, and it would join this list only if the agency grants assistance. These are shown so the pending application can be read against the agency’s own practice rather than against nothing.

ProjectWhereTermYears
Bradford Allen Hospitality, formerly Browning Hotels
The closest comparison on the list: a hotel.
2038 Old Country Road2023–20274
Atlantis Marine World Aquarium
Downtown, and built by the same developer. The aquarium has held an IDA agreement since 1999, amended repeatedly — most recently in 2025.
431 and 428 East Main Street2016–2030 and 2017–202714
Peconic Crossing
Downtown apartments.
11 West Main Street2018–202810
331 East Main, The Shipyard
Downtown mixed use.
331 East Main Street2021–203211
Restaurant Depot
Commercial.
756 Old Country Road2024–203410
Island Water Park, Scott’s Pointe
Commercial recreation.
Middle Country Road, Calverton2022–203210
Riverhead Apartments, Georgica Green Ventures
Affordable housing, which the agency treats differently.
221 East Main Street2020–205030
Riverhead Housing LP, River Pointe
Affordable housing.
821 East Main Street2024–205430

The organized opposition, and who is behind it

Show who is organizing against the subsidy, and what they argue

The petitions and the Riverhead Watch blog are the work of John McAuliff, a Riverhead resident and non-profit executive director who has blogged since 2006. He is the same John McAuliff who has spoken against the project at Town Board hearings in July and August 2025 and again in June and August 2026, quoted elsewhere on this page. Naming him is not a mark against the arguments — a resident who shows up for years and organizes is doing exactly what residents are supposed to do. It is here because “a petition,” “a blog” and “a speaker at the podium” read as three independent currents of opposition when they are one, and a reader weighing how much opposition exists should have that.

No Hotel/Condo in Riverhead Town Square135 of 200
Opened July 2, 2025, three weeks before the qualified-and-eligible hearing, addressed to the Town Board.
Not to compromise the square’s vista and character with a five-storey hotel and condominium on its east side; not to approve J. Petrocelli as master developer if he insisted on buying town-owned land for it; and to open competitive public bidding first.
No IDA Subsidy for Town Square Hotel33 of 50
Opened August 8, 2026, three days after the Town Board approved the site plan and five days after the agency took the application in, addressed to the Riverhead Industrial Development Agency.
That the agency “rigorously evaluate and completely reject” the request for tax subsidies to what it calls a five-storey, thirty-four-million-dollar luxury tourist hotel that would dominate half the new square.

Signature counts as of the writing of this page. An earlier petition sought to save the Craft’d bar from demolition; its author writes plainly that it failed.

The substantive argument, set out in a letter published in the Riverhead News-Review on July 10, 2025 and on the blog: that eminent domain is a power meant for roads, schools and hospitals rather than for handing public land to a private developer; that five-storey buildings on both sides would wall in the open space the square was meant to create, the west side having been spared in 2025 and the east side not; that a hotel could go on the riverfront near Spicey’s on West Main Street instead; and that Riverhead would do better with an open park along the lines of Greenport’s Mitchell Park.

What this page does not take from it: His case also includes a claim about the developer’s political donations. This page has not checked it against campaign filings, does not repeat it as fact, and relies on it for nothing. Some of the illustrative material on the blog and the petitions is generated by ChatGPT — the author says so himself, and notes in one case that the image “contains errors.” Every figure on this page comes from the Town’s own filings, the agency’s own records, the lease agreement, or named reporting.

This belongs beside the abatement because that is the one decision on this project still open, and because the agency must hold a public hearing before it decides. That hearing has not been scheduled. Whatever a reader makes of these petitions, it is the moment when support and objection both formally count.

Public assets committed to the building, none of them priced

Guest parking in public lots — to be paid for
Hotel guests use valet service, with cars parked in the public lot behind the Suffolk Theater until the garage is built, then in the garage on a pay-to-reserve and pay-to-park basis. This one is not free: the developer’s attorney said in June 2026 that his client was negotiating to pay for roughly 100 spaces in the interim lot. What it will pay has not been published, and the agreement did not exist when the site plan was approved two months later.
Easements and staging licenses over Town land
Annexed to the Master Developer Agreement as Exhibits C through F: a non-exclusive license to stage construction over Lots 12 and 13, an exclusive staging license over the retained portion of Lot 14, an easement for utilities and drainage under the retained portion of Lot 13, a driveway access easement from Heidi Behr Way across portions of Lots 14 and 23, and an easement for grease traps on Lot 15. Granted for the term of construction rather than sold.
Stormwater onto Town land
Stormwater from the hotel is directed to 25 leaching galleys on the adjacent town square property, under an agreement with the Town.
Access across the square
The hotel’s lower-level parking is reached from Heidi Behr Way through the town square parcel, under an agreement with the Town.

None of these is improper and all are ordinary in a public-private downtown project. The parking is to be paid for. They are listed together because the grant table and the developer’s budget are both cash ledgers, and a reader who adds those two up has still not seen any of this. Maintenance of the square used to sit in this list; it does not belong here, because it has a price and the money runs the other way — see what the Town pays, above.

The net effect on reserves

What it does to the fund balance

Both draws come out of accumulated surplus rather than new borrowing, which puts them squarely inside what the Town’s reserve policy governs.

Acquisition offer for 111 East Main StreetAuthorized amount$1,950,000
Authorized September 1, 2026, explicitly from the General Fund balance. Could rise if the owner pursues more in court. Board members said at the May hearing that the money could later be restored to fund balance if the Town eventually sold the property on for redevelopment — the same structure used for the hotel parcels, but with no buyer, no price and no agreement behind it.
Town Square note paydownBooked by the Town$1,874,218
Booked by resolution 2026-762 of August 4, 2026 against the General Fund’s Appropriated Fund Balance, beside $122,500 of rent. The July plan, resolution 2026-641, was rent and the net proceeds of the 127 East Main Street sale. The developer’s six-month extension delayed the sale, and the fund balance is to be reimbursed once it closes.
Unassigned, 12/31/2025
$28,829,513
41.7% of appropriations
Both draws
$3,824,218
13.3% of the balance
Left afterwards
$25,005,295
36.2% of appropriations
Policy floor
15%
$10,366,974; no ceiling (Res. 918 of 2011)
The verdict:
Money running the other way: Both draws have money running the other way against them, though only one of them is contracted. The pre-possession lease has the developer paying the Town $17,500 a month to August 2026 and $19,000 a month through the six-month extension, set deliberately at the Town’s own debt service on the land. And if the sale has not closed by March 14, 2027 the developer must remit $2,493,750 — an obligation the agreement makes “absolute and unconditional” — which the Town may apply straight to the debt. Resolution 2026-762 itself says the fund balance “will be reimbursed for the amount utilized” once the sale is complete. Retiring the note out of surplus was not surplus spent and gone; it was surplus advanced against a contracted receipt, and it saved the Town a fifteen-year bond carrying more than $500,000 of interest. The 111 East Main Street draw is different in kind: the Board has said that money could come back if the parcel is sold on for redevelopment, but unlike the hotel parcels there is no buyer, no price and no signed agreement — only an intention.
Together the two draws leave the unassigned balance well above the 15% floor in the Town’s own fund balance policy. This is a real draw on surplus, it is comfortably affordable, and one of the two draws is due back: the resolution that made it says the fund balance will be reimbursed from the sale. All three things are true, and a page that reported only one of them would be misleading.

These are the audited December 31, 2025 balances against the 2026 adopted appropriations. They do not reflect anything that happened to fund balance during 2026, because no report covering 2026 has been filed.

Part 3

The property the Town took

One parcel taken by eminent domain, and what it may finally cost.

The taking of 111 East Main Street

Owner
The Place for Learning, which owns the real estate and operates the science center
Mortgage holders
Elifran LLC and Fralin LLC, whose attorneys filed notices of appearance after being served
Town's offer
$1,950,000 — State law requires the Town to make a formal written offer based on its own highest approved appraisal. $1.95 million is that appraisal.
$1,950,000 is a floor, not a ceiling: The owner may take the $1.95 million as full payment, or take it as an advance payment and keep seeking more in court. Once title vests the remaining dispute is usually only about money — whether the appraisal reflects fair value. So $1.95 million is a floor on what this parcel costs the Town, not a ceiling.

The parcel borders the Town Square site on its west side and officials have called it integral to the plan. Board members have repeatedly cited the lack of progress on redeveloping the building as their reason for condemning it — the science center had not begun its first phase and held no building permits, and its representatives cancelled a scheduled Town Board update in March 2026 as a roughly $1 million grant tied to the project neared its deadline.

Show what happened at the three-hour condemnation hearing
The hearing
The EDPL hearing on May 20, 2026 ran nearly three hours and was contentious enough that reporting described the line between public testimony and board debate as blurred, with members rebutting critics from the dais. The Town’s case was put by Community Development Director Dawn Thomas: the building is “vacant, deteriorated, substandard and blighted,” the science center’s 2020 proposal for a roughly 24,000 square foot facility with a planetarium had repeatedly shrunk despite years of extensions, and at an April work session it emerged that the organization “was experiencing financial difficulties and could not promise that the funding was available.” Environmental consultant Jeff Seeman added the flood argument: the square, the hotel and the East End Arts campus are being designed as one integrated flood mitigation system, and “one parcel would cause the other parcels to continue to flood unless they’re all systemically raised.” Council Member Joann Waski put the Town’s position in a line: “This is not about the science center. This is about 111 East Main Street.”
Nobody could say what it would cost
Asked at that hearing what the eminent domain process would cost, Town Attorney Erik Howard answered: “I don’t know. We don’t have an appraisal on the property yet.” No estimate was given for acquisition, appraisal, outside counsel, court costs or anything else. Claudette Bianco of Baiting Hollow told the Board she heard little concern from it about the cost to taxpayers, saying she was neither for the taking nor against it. The $1.95 million figure arrived three months later, and covers the offer alone.
What public purpose was stated
The Town’s published hearing notice stated the acquisition was “for general municipal purposes.” Several speakers, including Heart of Riverhead Civic Association president Cindy Clifford, questioned whether so general a statement identifies a specific enough public use to hold up in court. Former Supervisor Laura Jens-Smith argued the science center had bought the building with the Town’s encouragement, and said that if conversations had already taken place about alternative private development of the site, they were relevant and should be disclosed.

The $1.95 million offer passed unanimously, but the decision to take the property did not. It was carried 3-2 in April 2026 over the Supervisor’s objection, twice, and the findings that made it final passed 3-1 in June with two abstentions. The Board had backed off eminent domain a year earlier, in 2025, after the science center presented a two-phase plan and pledged to proceed.

Part 4

When it gets built

Six connected projects on one schedule running to 2030, and the pieces still undecided.

Six connected projects, running to 2030

August 6, 2026 work session, presented by Planning and Community Development Director Dawn Thomas

The Town described itself as “transitioning out of the planning role to a construction role.” Six projects are now tied to one schedule: the Town Square itself, the 94-room hotel, an adaptive playground, a riverfront amphitheatre, East Main Street streetscape work, and a structured parking garage.

  1. August 2026Hotel construction mobilises
    The foundation permit was expected within a week or two of the work session, following site plan and special permit approval.
  2. Fall 2026Parking garage design begins; East End Arts buildings move
    The Davis-Corwin building at 133 East Main Street shifts about ten feet east, and both it and the Benjamin House are raised to 13.5 feet to lift them out of the floodplain. Grant funding rather than Town taxpayers pays for this, according to the Town.
  3. Spring 2027Town Square construction starts
    It serves first as staging for the hotel, then takes underground drainage, electric, Wi-Fi, cable and fibre, then pavers and public programming elements.
  4. Summer 2027Adaptive playground
    Opening shortly after the square.
  5. Fall 2027East Main Street streetscape
    Peconic Avenue to East Avenue: narrowing Main Street, widening sidewalks, burying utilities, lighting, landscaping and space for outdoor dining. An extension east toward the aquarium is hoped for but not funded in this phase.
  6. Spring 2028Town Square opens
  7. Fall or winter 2028Hotel opens
    The developer’s own schedule presented in July 2025 had aimed at June 2027.
  8. Fall 2028 to fall 2030Parking garage built
    The last piece, and the one the hotel’s parking arrangement ultimately depends on.
It has slipped: The public half has moved later. In November 2024 the same official said Town Square and playground construction could begin as early as late summer or early autumn 2025; the current schedule places it in spring 2027 with an opening in spring 2028. The hotel, meanwhile, has gone from a June 2027 opening to fall or winter 2028. The Town cautions that the schedule remains subject to funding, weather and materials.

Streetscape construction will disrupt Main Street while it runs. The Town is considering a weekend shuttle from Town Hall to downtown businesses, every fifteen minutes, funded initially through the parking district with sponsorships or small fares possible later. Seven public engagement sessions are scheduled between September 2026 and 2030.

The garage: $17 million available, cost unknown until it is bid

Available
$17,000,000
Of which about $2M for design
Spaces, current sizing
504
1995 plan contemplated 589

The Town has about $17 million available for the structured parking garage, roughly $2 million of it for design, but said the total construction cost will not be known until the project goes out to bid. It is currently sized at about 504 spaces; Council Member Denise Merrifield noted the Town’s 1995 downtown vision plan contemplated 589. Size, construction method and circulation remain undetermined, and the Town is weighing whether a modular structure could allow later expansion. It is also applying for funding for a police substation inside it.

The garage is the backstop for every parking commitment made elsewhere in this project. Hotel guests are to park in the public lot behind the Suffolk Theater until it opens, then shift into the garage under an agreement with the Town. On the current schedule that is 2030 — four years of hotel operation, and two years of hotel occupancy, before the structure it depends on exists.

A $1.4 million grant for something not yet decided

The Board accepted a $1,400,000 Empire State Development award for the riverfront amphitheatre by resolution 2025-591 in July 2025. As of August 2026 the Town had not settled what it is building: whether the space includes a fixed amphitheatre, a temporary stage, seasonal programming or something else “remains undecided.” The area becomes a flexible riverfront performance and gathering space once the East End Arts buildings are moved and raised.

The square may also carry a veterans memorial, which the Town says is aided by the pending acquisition of 111 East Main Street and by funding transferred from a boathouse project that did not go forward.

The parking agreement did not exist when the hotel was approved

Show the parking terms, the arithmetic raised, and the Board's answer
What the agreement actually provides
The Master Developer Agreement sets out the shape of it. On completion of the hotel, the Town — acting through Parking District No. 1 rather than as the Town generally — is to enter a Parking Lot Lease Agreement with the hotel over part of the lot behind the Suffolk Theater. That lease expires when the garage is finished and an agreement for the hotel’s use of part of the garage takes effect, “with pay to reserve and pay to park per parking stall.” The Town also acknowledges in the agreement that, despite the site sitting inside the parking district, designated parking for hotel guests “is integral and necessary” for the use. The terms are to be negotiated by the Town Attorney, approved by Town Board resolution, and folded into the site plan approval — which is what had not happened by August 2026.
Why it is a fiscal question
The hotel site sits inside the Riverhead Parking District, a special taxing district established in 1967 and governed by the Town Board itself sitting as its trustees. Since the 2007 revitalisation zoning the Town has not required downtown residential or hotel developers to provide their own parking; they rely on municipal lots. The master developer agreement refers to a parking agreement, but at the August 4, 2026 approval it had not been negotiated. Town Attorney Erik Howard said it “will be negotiated shortly” and would be incorporated into the approval once complete.
The arithmetic raised
Martin Sendlewski, who chairs the Town’s own Parking District Advisory Committee, told the June 2026 hearing that the Main Street improvement plan would cut parking between Roanoke and East Avenues from 40 spaces to 21, and that the hotel’s valet area would remove several more. He noted that the First Street lot belongs to Riverhead Parking District No. 1 rather than to the Town generally, and argued that any agreement allocating public spaces to hotel use should come before the district’s trustees. He returned in August to ask how a site plan could be approved before the parking agreement or even its framework existed, with the planned garage “likely years off.”
What the Board said
Council members defended the approval. Joann Waski called the emergence of a downtown parking problem “a good thing… because it means that what has been happening downtown is working,” and told a resident she could personally assure him downtown businesses would not be harmed. Denise Merrifield said no one had raised parking objections to the science center’s plan for the opposite side of the square, which she called unpersuasive as a standard.
Part 5

The record

How the Board voted, what residents said, how it got here, and what this page still cannot tell you.

The money votes were unanimous. The taking was not.

Every money vote on this project has been unanimous. Every vote to take the property was not. The Supervisor voted against the acquisition in April 2026 and against setting the condemnation hearing two weeks later, then abstained when the findings were adopted in June. Councilman Kern did the same, and had voted no on the leasehold findings a year earlier. Three members — Rothwell, Merrifield and Waski — carried it each time.

Show every recorded vote, with resolution numbers
2025-316
Sets the public hearing on acquiring SNR Bar 25 Corp’s lease — the Craft’d bar at 127 East Main Street
April 1, 2025
Adopted unanimously
2025-499
Findings and determination under the Eminent Domain Procedure Law — the Craft’d leasehold
June 3, 2025 · Kern voted no.
Adopted 4–1
2025-647
Budget adjustment funding a $120,000 settlement offer to the tenant of 127 East Main Street
August 5, 2025
Adopted unanimously
2025-696
Designates J. Petrocelli Riverhead Town Square LLC a qualified and eligible sponsor and authorizes the master developer agreement — the vote that permits the $2,625,000 land sale without competitive bidding
August 5, 2025
Adopted unanimously
2025-705
Budget transfer for Capital Project #12101, Town Square Properties
August 19, 2025
Adopted unanimously
2025-778
A second budget adjustment for the same tenant, covering the rise from the $120,000 offer to the $170,000 settlement
September 16, 2025
Adopted unanimously
2025-591
Accepts a $1,400,000 New York State ESD grant for the Town Square riverfront amphitheatre
July 1, 2025
Adopted unanimously
2026-327
Affirms the prior authorization to acquire 111 East Main Street
April 7, 2026 · Supervisor Halpin and Councilman Kern voted no.
Adopted 3–2
2026-404
Sets the public hearing on condemning the parcel
April 21, 2026 · Halpin and Kern voted no again.
Adopted 3–2
2026-553
Findings and determination under the Eminent Domain Procedure Law — fee title to 111 East Main Street
June 2, 2026 · Halpin and Kern abstained rather than voting no.
Adopted 3–1
2026-566
Closes Capital Project #12101, Town Square Properties
June 16, 2026
Adopted unanimously
2026-641
Budget adjustment to pay down the Town Square bond anticipation note
July 7, 2026
Adopted unanimously
2026-746
Grants special permit and site plan approval for the Peconic River Hotel
August 4, 2026
Adopted unanimously
2026-762
Ratifies a budget adjustment temporarily amending the funding source for the note paydown
August 4, 2026
Adopted unanimously

What residents said, and what they were told

The money votes have been unanimous, but the hearings have not been quiet. These are the objections actually made on the record, and the answers actually given.

Show what each speaker said, hearing by hearing
Angela DeVito, South Jamesport — July 2025
Asked the Board to hold the qualified-and-eligible hearing open thirty days because the documents presented were not available to the public before or at the hearing; they were posted the following day. She also questioned what standard the Town used to judge the finances of J. Petrocelli Riverhead Town Square LLC, the new entity replacing the one originally designated master developer, noting the Board had no information about that LLC’s own finances or development record.
Adele Wallach, Riverhead — August 2025
Questioned the clause crediting the developer against the purchase price for its 2022 grant-match pledge, and asked whether that pledge had effectively obligated the Town to the qualified-and-eligible designation.
John McAuliff, Riverhead — August 2025 and August 2026
Asked the Board to pause until September so residents could examine the financials, and questioned whether a five-storey hotel is the best use of the site. A year later he argued the hotel would hurt nearby businesses whose customers already struggle to park, and called the design a “five-story box” that would block views of the Peconic River and sunlight to the art galleries next door. The developer’s team answered that the building was designed to suit the neighbourhood and that its upper floors step back to reduce visual impact.
Kathy McGraw, Northville — June 2026
Argued the application was being treated as a final site plan while processed as a preliminary one, contrary to the Town’s two-step code. Community Development Administrator Dawn Thomas answered that the Town has long used a single application and a single hearing, followed by approval with conditions and later signoff.
Laura Jens-Smith, Laurel — June and August 2026
Called for a cost-benefit analysis of the total public investment — land conveyed, easements, parking commitments, infrastructure and future maintenance — and for a statement separating infrastructure costs borne by the developer from those ultimately borne by taxpayers. She asked whether the Town had evaluated the loss of assessed value, property tax and school tax revenue in dropping the condominiums for a hotel-only plan, and argued the approval was premature given the site’s designation as a potential environmental justice area.
Cindy Clifford, Heart of Riverhead Civic Association president — May 2026
Told the Board she understood that “just saying this is for public use is not going to cut it” in the eyes of a court, and argued the science center would itself have drawn visitors from the aquarium and produced the foot traffic the square was promised to create.
Colin Tooker, Riverhead — May 2026
Asked what the eminent domain process was going to cost. The Town Attorney answered that he did not know, because there was no appraisal yet. Claudette Bianco of Baiting Hollow followed by saying she heard little concern from the Board about the cost to taxpayers, while stating she was neither for the taking nor against it.
Desmond Wong, Baiting Hollow — May and June 2026
At the condemnation hearing: “The question in front of this board is not really should we seize this parcel. The question is why does every problem in this downtown have the same solution?” A month later, on the hotel’s parking arrangement, he objected that it depends on infrastructure that does not exist yet — the First Street garage, which on the Town’s own August 2026 schedule is not finished until 2030. “That is not a parking plan — that is a hope.”
Martin Sendlewski, Parking District Advisory Committee chair — June and August 2026
Questioned approving the site plan before the parking agreement existed, and set out the arithmetic of spaces being lost on Main Street.
The Town's answers: Dawn Thomas told the June 2026 hearing that the cost-benefit analysis Jens-Smith asked for was performed by Perkins Eastman as part of the State Downtown Revitalization Initiative strategic investment plan, that grant funding rather than Town taxpayers is paying to relocate and preserve the East End Arts buildings, and that the hotel itself is not being built with taxpayer money. Town Attorney Erik Howard said the Suffolk County Planning Commission’s environmental justice remarks were comments rather than binding conditions, and that the Board was free to vote.

Support was also on the record and is not incidental: roughly twenty speakers appeared at the 2025 hearing, the developer submitted nine letters from local businesses and nonprofits — including the Long Island Science Center, whose building the Town later moved to condemn — and business owners including Suffolk Theater’s Bob Castaldi and Riverhead Flower Shop’s Peggy Kneski spoke in favour. Fifteen letters of objection were filed before the August 2025 vote.

The exchanges have not always been temperate. Supervisor Tim Hubbard, voting yes in August 2025, called requests to delay “disingenuous” and speculated about objectors’ party affiliation; Claudette Bianco of Baiting Hollow told him taxpayers “paid for the right to disagree with you,” and he replied “if the shoe fits, wear it.” In June 2026 Council Member Denise Merrifield pressed Jens-Smith to state whether she chairs the Riverhead Democratic Committee, which Jens-Smith declined to do, saying the same standard would then have to apply to board members and Town officials. Joann Waski pointed to the eleven members of the public in the room as evidence that opposition was not widespread.

How it got here

Seventeen dated steps from the first two state grants in December 2019 to the schedule published in August 2026. Everything here is drawn from a named source.

Show the full timeline, December 2019 to August 2026
December 2019Money
Two state grants seed the idea
The Long Island Regional Economic Development Council awarded $775,000 to the Long Island Science Center for its expansion and $800,000 to the Town, in the same round, to create a town square opening the riverfront to Main Street.
Source: RiverheadLOCAL, February 4, 2020
February 2020Property
The science center moves to buy the old Swezey’s building
Board president Laurence Oxman announced the purchase of 111 East Main Street, the former Swezey’s Department Store, for a permanent home — 24,000 square feet over two floors, quadruple its existing space. Plans were unveiled at a February 14 press conference where Supervisor Yvette Aguiar called it “a heart transplant for Riverhead.” The completed purchase, in April 2020, was $1.45 million.
Source: RiverheadLOCAL, February 4 and 14, 2020; April 1, 2025
May 2021Property
The Town buys three buildings east of the science center
Two were demolished, creating the green space that became the public plaza. The third, 127 East Main Street, was left standing and cost the Town $2,650,000 — a two-storey building with two ground-floor storefronts and offices above, partly tenanted. One storefront was leased to the bar Craft’d; the other now houses the Riverhead Chamber of Commerce and the Business Improvement District.
Source: RiverheadLOCAL, April 1, 2025
August 15, 2021Money
A bond anticipation note funds the property purchases
A $2,800,000 note for “Purchase of Town Square properties.” It stood at $2,725,000 at the close of 2025 and reached its maturity date on August 14, 2026 — five years after issue, which is the statutory outside limit for converting a capital note into long-term bonds.
Source: 2025 Annual Financial Report, Statement of Indebtedness
July 2025Build
The developer files a $32.7M private budget for review
The Community Development Agency’s Qualified and Eligible review produced a CPA verification of the developer’s financial capacity and a development budget totalling $32,672,889.76 — about 97% of it a construction loan and developer equity, with a $1,000,000 Restore NY grant the only public money in it. J. Petrocelli had already been designated master developer in April 2022; this was the review that had to clear before the land could change hands.
Source: Town of Riverhead, Town Square QE Documents
August 5, 2025Money
The Board approves the developer agreement and the land sale
Resolution 2025-696 declared J. Petrocelli Riverhead Town Square LLC a qualified and eligible sponsor under the State Urban Renewal Law, which lets the Town sell it the land — including the standing building at 127 East Main Street — for $2,625,000 without competitive bidding. The same action authorized the master developer agreement, under which the Town pays the company a construction management fee of 7% of the cost of building the public plaza, playground, walkways and amphitheatre, and takes on certain maintenance obligations for them. Adopted unanimously, moved by Rothwell and seconded by Kern, after fifteen letters of objection and a run of critical public comment.
Source: Town Board resolution 2025-696; RiverheadLOCAL, August 6, 2025
April–September 2025Legal
The Craft’d leasehold is condemned, then settled for $170,000
The Town owned 127 East Main Street but not the bar inside it: when it took title in 2021 it took the building subject to SNR Bar 25 Corp’s 2018 lease, whose two five-year renewal options ran the tenancy to November 2033. Clearing the site meant buying that lease out. Public hearings were set unanimously in April, with Supervisor Tim Hubbard saying he would invite the science center’s board to a work session and that the Town would help Craft’d relocate. Co-owner Sean Kenna told the Board he was disappointed by what he called a communication breakdown. The Board funded a $120,000 offer on August 5; a State Supreme Court judge granted the Town’s petition on August 27 and the order was filed the next day; the settlement was signed September 3 at $170,000, with a second budget adjustment on September 16 covering the difference. Craft’d closed on September 20.
Source: RiverheadLOCAL, April 3, August 29 and September 11, 2025; Town Board resolutions 2025-647 and 2025-778
December 12, 2025Build
Groundbreaking
The Town held its groundbreaking ceremony and published a full accounting of the public money behind the project — $34.9 million across seven federal, state and county awards. Supervisor Tim Hubbard called it “a vision that has been 30 years in the making.”
Source: Town of Riverhead press release, December 12, 2025
March 2026Legal
The Town revives eminent domain after the science center stalls
The nonprofit had not begun the first phase of its expansion and held no building permits. Its representatives cancelled a scheduled Town Board update at the last minute as a roughly $1 million grant tied to the project neared its deadline. Councilwoman Merrifield: “I have absolutely no hope that the Science Center will ever come to fruition in the time schedule that we need for the activation of our Town Square.” The Board had backed off eminent domain a year earlier when the science center presented a two-phase plan.
Source: Riverhead News-Review, March 27, 2026
April–June 2026Legal
The Board votes to take the property — over the Supervisor’s objection
Three votes, none unanimous. The acquisition was affirmed 3-2 on April 7 and the condemnation hearing set 3-2 on April 21, with Supervisor Halpin and Councilman Kern against both. The findings under the Eminent Domain Procedure Law passed 3-1 on June 2 with the same two abstaining.
Source: Town Board resolutions 2026-327, 2026-404 and 2026-553
April 1, 2025Legal
Two condemnations, not one
The Town moved on both buildings flanking the square at once: buying out the Craft’d bar’s lease inside its own building at 127 East Main Street, and acquiring the science center’s building at 111 East Main. Clearing both would let the Town convey each to private developers. The leasehold was settled by budget adjustments in August and September 2025; the science center’s building took another eighteen months.
Source: RiverheadLOCAL, April 1, 2025; Town Board resolutions 2025-316, 2025-499, 2025-647 and 2025-778
June 18, 2026Legal
The Town publishes its determination to take 111 East Main Street
Publication started a 30-day window in which the owner could have brought an action challenging the condemnation itself. No such challenge was filed, according to court filings reviewed by RiverheadLOCAL.
Source: RiverheadLOCAL, September 2, 2026
July 7, 2026Money
The Board votes to pay down the Town Square note from the hotel-site sale
Resolution 2026-641, adopted unanimously: a budget adjustment to pay down the note, due August 14, with $32,000 to $57,000 of rent from the pre-possession lease and the remaining net proceeds of the $2,625,000 sale of 127 East Main Street, of which $660,000 is contractually designated to Town Square projects. It names no fund balance and states no total.
Source: Town Board resolution 2026-641, July 7, 2026
August 4, 2026Build
The Peconic River Hotel wins site plan and special permit approval
A unanimous 5-0 vote on resolution 2026-746, for a five-storey, 94-room Tapestry by Hilton at 117–127 East Main Street — 69,738 square feet on about 0.42 acres, with retail, a restaurant, a café and nine staff parking spaces below. The same meeting ratified resolution 2026-762. The developer had used its right to six more months of site work, delaying the sale, so in the interim the note would be paid with $1,874,218 of General Fund appropriated fund balance and $122,500 of rent, and the fund balance “will be reimbursed” once the sale is complete.
Source: RiverheadLOCAL, August 5, 2026; Town Board resolutions 2026-746 and 2026-762
August 6, 2026Build
The Town publishes a schedule running to 2030
Six connected projects were put on one timetable at a Town Board work session: hotel construction mobilising that month, garage design in the autumn, Town Square construction in spring 2027 and opening in spring 2028, streetscape work in autumn 2027, and the parking garage built between 2028 and 2030. The public half had slipped: in November 2024 the same official said Town Square and playground construction could start as early as late summer 2025.
Source: RiverheadLOCAL, August 7, 2026
August 26, 2026Legal
The court issues a vesting order
Under the State’s Eminent Domain Procedure Law, title passes to the Town once the vesting order and the acquisition map are filed with the county clerk.
Source: RiverheadLOCAL, September 2, 2026
September 1, 2026Money
The Board authorizes a $1.95 million offer, payable from fund balance
A unanimous vote approving the Town’s appraisal at $1,950,000 and authorizing its attorneys to transmit that offer to The Place for Learning, with the sum to be paid out of the General Fund balance. The resolution also authorizes the town financial administrator to establish a budget for the expenditure.
Source: RiverheadLOCAL, September 2, 2026
October 6, 2026Build
The Town seeks proposals for a destination attraction at 111 East Main Street
A unanimous vote authorizing the Town Clerk to publish a Request for Proposals, in the October 15 News-Review, for “Redevelopment and Operation of a Destination Attraction at 111 East Main Street.” The Town “seeks proposals from qualified developers, attraction operators, entertainment companies, destination retailers, hospitality groups, and public-private partnership teams.” The fiscal impact statement marks no cost to the Town. No developer had been chosen in the Board records through November 5, 2026.
Source: Town Board resolution 2026-922, agenda packet, October 6, 2026

What this page cannot tell you

  • How much of the note was paid down, and when is the fund balance repaid? Resolution 2026-762 moved $1,996,718 to debt service for it, $1,874,218 of that from fund balance to be reimbursed from the sale, but no 2026 financial report exists yet to show either.
  • Will The Place for Learning accept the $1.95 million as full payment, or take it as an advance and litigate for more? That answer sets the real acquisition cost.
  • What is the 7% construction management fee worth in dollars? The agreement fixes the rate and caps nothing. It is charged on the total construction cost of the public plaza, playground, amphitheatre and East End Arts relocation, and that cost has not been published.
  • What does the Town actually get for $150,000 a year? The duties are Exhibit J to the Master Developer Agreement, and Exhibit J is not attached to the copy the Town publishes. The fee is settled; the obligations bought with it are not public, and the agreement setting them out has still to be negotiated.
  • What will the hotel pay for its roughly 100 interim parking spaces, and what will pay-to-park in the garage cost it? Both agreements were still unnegotiated when the site plan was approved.
  • What will the Industrial Development Agency grant, and what is it worth? A twenty-year PILOT has been requested, along with sales tax and mortgage recording tax relief. Nobody outside the agency has read the application, no hearing has been scheduled, and the school district — which stands to forgo the largest share — has no vote in it.
  • What will the developer pay for the roughly 100 public parking spaces it is negotiating to use, and for how long? The agreement did not exist when the site plan was approved.
  • What did dropping the twelve condominiums cost the tax base? Owner-occupied units would have been taxable residential property; the question was asked of the Board in June 2026 and has not been answered publicly.
  • What has the Town itself spent in total — land, demolition, site work, flood mitigation, outside counsel for the condemnations — as opposed to what the developer is spending? The developer’s budget is published; no equivalent consolidated figure for the Town’s own outlay is. This is the cost-benefit statement residents asked for in June 2026 and did not receive.

These are answerable — at a Town Board meeting, or by a records request. The rules for speaking are on the Town Board Votes page, and the note itself is itemised on Capital & Debt.

Part 6

Process questions

Where the Town's own documents sit alongside the statutes they were written under, and what a resident would need to ask to close the gap.

Process questions a resident could put to the Board

Read this first: This page is not written by a lawyer and none of what follows is legal advice or an allegation that the Town broke any law. Each item sets a statutory requirement beside the text of the agreement and says what the public record does and does not show. Municipal records that are not published are not thereby missing: most of these would be answered by a document request, and several may already have been done correctly out of public view.

Every item names the one document that would settle it. That is the point of the section — not to reach a verdict, but to make the questions specific enough that they can actually be answered.

1Were the two service contracts procured under the Town’s own procurement policy?Sharpest
What the rule requires
General Municipal Law §103(1) requires competitive bidding for “contracts for public work involving an expenditure of more than thirty-five thousand dollars” and for “purchase contracts (including contracts for service work)… more than twenty thousand dollars.” Where bidding is not required, §104-b obliges every town to adopt a policy that prescribes a procedure for “documenting the basis for any determination that competitive bidding is not required by law,” and requires “justification and documentation of any contract awarded to other than the lowest responsible dollar offeror.” The Town’s own Purchasing page commits to both, and says the policy exists to guard “against favoritism.”
What the agreement says
The agreement has the Town buying two things from the company it is selling the land to: operation and maintenance of the Town Square at $150,000 a year for ten years, and construction management of the public works at 7% of total construction cost, uncapped, across three agreements styled “Consultant/Professional Services Agreement.” Running a public park is service work; whether it is a professional service is at least arguable.
What the record shows
Urban Renewal Law §507 lets a municipality sell land to a qualified and eligible sponsor without bidding. It does not address buying services. The agreement’s recitals, read in full, recite the Article 15 hearing, resolutions 2022-235 and 2022-325 and the SEQR position. They recite nothing about competitive bidding, an exemption determination, or the procurement policy.
What would settle it
The Town’s §104-b determination for these two procurements, if one was made. That is an ordinary public record.
2Does the fee credit put the same party on both sides of the number?Sharpest
What the rule requires
A 2002 opinion of the State Comptroller holds that a firm may not be engaged both as construction manager acting on a town’s behalf and as a prime contractor on the same project. The facts here are not those facts, but the structure invites the same question.
What the agreement says
Section 3.04(a): “the Town reserves the right at its option to give Master Developer a credit against the balance of the Purchase Price due at Closing for amounts which may be then due or to become due to Master Developer under any of the three Construction Management Agreements.”
What the record shows
The rate is fixed at 7%. The construction cost it is charged on has not been published, and there is no cap. A larger construction management fee therefore means less cash to the Town for the land, and the same company is on both sides of that trade.
What would settle it
A published cost estimate for the public works, and a statement of whether the Town intends to exercise the credit.
3Did this disposition need state approval, and did it get it?Open
What the rule requires
General Municipal Law §507(2)(d)(3) provides that a sale to a qualified and eligible sponsor “shall, in the case of projects aided by a state loan, periodic subsidy or capital grant or in which application has been made for such loan, subsidy or grant, be approved by the commissioner.” §502(11) defines the commissioner as the Commissioner of Housing and Community Renewal.
What the agreement says
The recitals make no reference to approval by any state commissioner.
What the record shows
The project holds $4,200,000 from the Downtown Revitalization Initiative, $3,200,000 from Empire State Development, $500,000 from State Parks and $400,000 in Brownfield Opportunity Area funds. On a plain reading those are state capital grants aiding the project. There is a real counter-reading: “state loan, periodic subsidy or capital grant” inside the Urban Renewal article may mean urban renewal aid administered by that same commissioner rather than any state grant at all. Both readings are live and this page cannot resolve which is right.
What would settle it
Either an approval on file, or the Town Attorney’s position on why the clause does not apply.
4What is the Town buying for $1,500,000?Sharpest
What the rule requires
Not a statute — a governance question. A board voting a ten-year obligation should be able to say what it is obliged to receive.
What the agreement says
The fee is fixed and explicitly carved out of what remains to be negotiated: all terms are to be settled at or before closing “with the exception of annual fee set at $150,000.00 per year for 10 year term.” The duties are “a list of responsibilities for operation/maintenance attached hereto as Exhibit ‘J’.”
What the record shows
The copy the Town publishes runs to 124 pages and ends with the third construction management agreement. Exhibits A through I are all attached. Exhibit J is not.
What would settle it
Publication of Exhibit J.
5Did the parking district act on its own property?Open
What the rule requires
A special district holds its own property and its own funds. The Town Board sits as the district’s trustees, but it acts in a separate capacity when it does.
What the agreement says
The agreement recites that “the remainder of Lot 23 shall remain the property of the Riverhead Public Parking District No. 1,” grants a driveway access easement across part of Lot 23, and provides that the Town, “by and through Parking District No. 1,” will enter a parking lot lease with the hotel.
What the record shows
The Town plainly knows this distinction: on the same evening as the qualified-and-eligible hearing it held a separate public hearing on transferring 2,784 square feet from the Parking District to the Town for the garage. Martin Sendlewski, who chairs the Town’s own Parking District Advisory Committee, asked in 2026 whether agreements allocating public spaces to the hotel should come before the district trustees.
What would settle it
District-level resolutions authorizing the Lot 23 easement and the parking lease.
6What established that $2,625,000 was the right price?Open
What the rule requires
The alternative route in §507(2)(c) requires a sponsor to pay “the minimum price or rental fixed by the agency” and to match any higher bid. The route the Town used, §507(2)(d), requires instead that the price and all other essential terms appear in the published notice.
What the agreement says
The price is $2,625,000, reduced by $660,000 of grant-match credits and a further $150,000 if the square is open by closing, with construction management fees creditable on top at the Town’s option.
What the record shows
The price and the 7% fee were public nineteen days before the hearing, which is well beyond the ten days the statute requires — an earlier draft of this page suggested otherwise and was wrong. What is still not in the record reviewed here is any appraisal, or any agency determination fixing a minimum price, against which $2,625,000 could be tested.
What would settle it
The Community Development Agency’s determination of the minimum price, and any appraisal behind it.
7Can a site plan be approved on a condition that does not exist yet?Open
What the rule requires
A condition of approval is normally something the board can read.
What the agreement says
The agreement provides that the parking agreement terms “shall be negotiated and prepared by the Office of the Town Attorney with requisite approval by Resolution of the Town Board and incorporated into site plan approval.”
What the record shows
Site plan and special permit approval passed 5-0 on August 4, 2026. The Town Attorney told the meeting the parking agreement “will be negotiated shortly” and would be incorporated once complete.
What would settle it
The executed parking agreement and the resolution approving it.
8Should the Town have made a tax break a material requirement of its own contract?Judgment call
What the rule requires
A judgment question rather than a legal one. The Industrial Development Agency is a separate public benefit corporation and is not bound by what the Town Board signs.
What the agreement says
The recitals state that obtaining a PILOT agreement “is a material requirement of this Agreement,” that its payment, escalation and term must be “acceptable to Master Developer in its sole, but reasonable, discretion,” and that failing to obtain one “shall have a material adverse impact on the economics of the transactions contemplated in this Agreement.”
What the record shows
The Town signed that in August 2025. The agency accepted the application for review on August 3, 2026, has approved nothing, and has scheduled no hearing.
What would settle it
Nothing documentary. It is a question about whether the commitment was appropriate to make, which is for residents and the Board.
What cuts the Town's way: Several things cut the Town’s way and belong in the same frame. The hearing was noticed three weeks ahead, not the statutory ten days, and the price and the 7% construction management fee were reported publicly nineteen days before it — this was disclosed, not buried. Selling urban renewal land to a designated sponsor without competitive bidding is an ordinary and lawful route, and the Town Attorney said so on the record in May 2025. The developer takes the property as is with no warranty including environmental condition, bears the whole cost of demolition, carries $5,000,000 of liability insurance, must post a performance bond, and owes the Town $300,000 if it defaults on the construction management agreements. And §104-b(5) says in terms that “the unintentional failure to fully comply with the provisions of this section shall not be grounds to void action taken or give rise to a cause of action” — so a documentation gap, if there is one, is a transparency problem rather than a legal vulnerability.

None of this establishes that anything was done improperly. It establishes that a resident reading the Town’s own documents alongside the statutes they were written under is left with specific, answerable questions — and that the answers are not currently published.

Sources

Show all sources
Independent public-records guide for Riverhead residents.

Riverhead Budget Live is an independent project. It is not run, approved, or endorsed by the Town of Riverhead. The site organizes public information and provides analysis; it is not a substitute for the Town’s official records. Check the linked source documents before relying on an important figure. Basic, aggregated site-usage statistics are collected through Google Analytics. You do not need an account to use this site. There are no ads. If you’d like to help cover its costs, you can chip in on Ko-fi.